Guidelines of the President of the Energy Regulatory Office on doubts concerning the connection of installations operating in the cable pooling scheme

20 May 2024 | Knowledge, News, The Right Focus

The EU is seeking to electrify not only the energy sector but also many other sectors of the economy. As a result, the demand for electricity is increasing. The draft update of Poland’s Electricity Policy until 2040 (PEP2040)[1] foresees an increase in electricity demand of around 2,000 ktoe in 2030 compared to 2020, with the application of energy-saving solutions. As a total of 8,356 MW of coal and brown coal unit capacity is planned to be withdrawn by 2030,[2] the demand for power from renewable energy sources will also increase. At the same time, experts estimate that the deficit in installed renewable energy capacity is already 16 GW due to the increasing number of connection refusals.[3] The new PEP2040 not only sets higher targets for RES development, but also specifies the guidelines that electricity system operators (ESOs) must take into account in their grid development plans. Among other things, the policy talks about the dynamic development of new capacity, including zero-carbon capacity in the electricity sector.

The full development of the RES industry therefore requires not only a friendly regulatory environment, but also:

  • Increasing the capacity of electricity grids
  • Removing barriers to connecting new generation capacity

Cable pooling is a solution that has the potential to accelerate the increase of renewable energy capacity, but also raises a number of questions. We analyse the guidelines of the President of the Energy Regulatory Office (URE)[4] regarding the installation of RES in this scheme and reiterate our earlier discussion of the guidelines of the URE President on doubts about the public and commercial grid connection of RES installations.

What is cable pooling

Cable pooling is the sharing of a connection by generation installations which usually have different operating characteristics (e.g. PV and onshore).

In accordance with the Energy Act, two or more RES installations belonging to one or more entities may be connected to the electricity grid with a rated voltage higher than 1 kV at a single location.[5]

In the cable pooling scheme, it is necessary to obtain connection conditions and then conclude a single connection agreement.[6] In this case, in accordance with the law, the agreement must contain additional elements, in particular:

  • A cable pooling agreement concluded by all entities sharing the connection, together with the identification of the representative party concluding the agreement
  • The definition of the rules for the joint exercise of rights and obligations under:
    • Connection conditions
    • Connection agreement
    • Agreement for the provision of electricity transmission or distribution services
  • Definition of the rules for the sharing of sets of equipment for power evacuation up to the demarcation point between the ownership of the energy company’s grid and the installations of the connected entities

Conditions for installations in a cable pooling system

The implementation of a cable pooling system is based on the use of a hybrid RES installation.[7]

This is an installation consisting of equipment connected to the electricity grid at a single location and generating electricity exclusively from RES, which differ in the type and availability characteristics of the electricity generated.

The set of such equipment must meet the following conditions:

  • None of the generating equipment may have an installed electrical capacity greater than 80% of the total installed electrical capacity of that set of equipment
  • The evacuation of power from the equipment in that set to the electricity grid is carried out by a device connecting that set to the electricity grid and designed to convert the energy to the conditions necessary for its injection into that grid
  • The set of equipment includes an energy storage device for storing electricity from the generating equipment included in the set, where the proportion of electricity from the generating equipment injected into the electricity grid via the energy storage device to the total amount of electricity injected into the grid is not less than 5% per year, not including electricity withdrawn from the grid

The connection of hybrid RES plants raises a number of questions and practical problems, such as whether it is possible to add more generation sources to an existing installation, whether the same technologies can be combined and what the rules are for applying for support schemes.

Let’s take a look at the guidelines issued by the President of the URE.

Guidelines of the President of the URE on cable pooling

In accordance with the guidelines of the President of the Energy Regulatory Office, cable pooling is applicable to new RES installations as well as to the expansion of existing RES installations with additional generation sources.

A connection may be shared on the basis of an application for connection conditions:

  • For the first grid connection of two or more RES installations
  • In a situation where connection conditions and the relevant agreement have been previously issued and concluded for the ‘first’ RES installation and the entity to be connected applies for connection of a second or subsequent RES installation
  • In a situation where one RES installation is connected to the grid (existing installation and a constructed connection) and the connected entity applies for the connection of a second or subsequent RES installation

Cable pooling also applies to installations connected to the grid prior to the adoption of cable pooling regulations.[8] Installations of the same or different technologies (e.g. two PV or PV and onshore) can share the connection. Cable pooling can be used by one owner or by several owners (in the latter case it is necessary to work out a cooperation model, including the appointment of an entity to conclude the connection agreement and a transmission/distribution service agreement for the whole installation).

The cable pooling regulations apply in the event of:

  • An increase in the declared connection capacity by an entity that has entered into a connection agreement involving cable pooling
  • A change in the technical parameters of the equipment and installations comprised in the connected cable pooling installation, including an increase in their installed electrical capacity

With regard to the use of a support scheme (FIT/FIP systems of RES auctions), a producer of energy in a ‘planned installation’ (to be added to an existing installation) is not entitled to use RES support schemes if the producer of energy in the ‘first’ installation is a beneficiary of the aforementioned schemes.

In conclusion, it can be expected that the practice of ESOs in connecting RES installations in the cable pooling scheme will be standardised, not only due to the position of the President of the URE, but above all due to a number of other factors, such as:

  • Growing energy demand
  • The gap created by the withdrawal of coal-fired units
  • The need to stabilise energy production from RES

Any questions? Contact us

Milena Kazanowska – Kędzierska

Aleksandra Pinkas

 

[1] Annex 1 to the EPCIP Transition scenario in market and technical conditions, p. 78

[2] Ibidem, p. 18.

[3] Cf. Forum Energii, RES pooling. Potential of cable pooling in Poland, p. 3, in which experts point out that grid operators refused the connection of 51 GW of RES capacity in 2022 alone.

[4] Information from the President of the Energy Regulatory Office no. 15/2024 of 22 March 2024 on the issues that cause the most frequent doubts regarding connection to the grid.

[5] Article 7(1f) of the Energy Law of 10 April 1997 (Journal of Laws of 2024, item 266), which provides that: “two or more RES installations belonging to one or more entities may be connected to the electricity grid with a rated voltage higher than 1 kV at a single connection point. The first sentence shall not apply to RES installations where the grid connection point is an installation of an end consumer”.

[6] Article 7(1g) of the Energy Law

[7] Article 2(11a) of the Renewable Energy Sources Act of 20 February 2015 (Journal of Laws of 2023, item 1436, as amended), the ‘RES Act

[8] i.e. before 1 October 2023, when the amendment of the RES Act in this respect came into force

Latest Knowledge

Banking sector overview | Banking today and tomorrow | June 2026

According to a statement published by GPW Benchmark, the reference rate administrator, and the Polish Financial Supervision Authority (KNF), which oversees the administrator, 31 December 2036 will be the last day on which the WIBID and WIBOR rates will be provided for all key fixing periods: 1 month (1M), 3 months (3M) and 6 months (6M).

How to correctly calculate length of service from 1 May 2026

New rules for calculating length of service have applied to private sector employers since the beginning of May 2026. With companies continuing to express concerns about the new framework, the Ministry of Family, Labour and Social Policy has addressed the most common questions. We look at the issues that are (still) troubling employers and how we can help.

Tax settlement agreement: A new tool in the General Tax Code

A draft bill amending the General Tax Code (No. UDER110) has been submitted for consideration by the Council of Ministers. The bill introduces the tax settlement agreement, a new form of amicable dispute resolution between taxpayers and the tax authority. The draft is open for inter-ministerial review and public consultation until 19 June, with the proposed date of entry into force being 1 January 2028. Below, we examine who may apply for a settlement agreement, when, and on what terms, and how the process may work in practice.

A revolutionary reform of Poland’s capital market – ETFs and the Qualified Investment Fund

Poland’s capital market is on the cusp of one of the most significant reforms in recent years, which will fundamentally reshape the regulatory framework for ETFs and introduce an entirely new investment vehicle: the Qualified Investment Fund (QIF/KFI). This is a response to market demands and presents an opportunity for Poland to close the gap with countries such as Luxembourg and Ireland, with the overarching objective of boosting competitiveness and stemming the outflow of investment capital abroad. The new regulations aim to deliver greater flexibility for investors and fund managers alike, while also aligning with current market trends and European standards. We examine what is changing in practice and what it means for all market participants.

Directive 2024/825 – the European Union’s response to greenwashing

Greenwashing poses one of the most significant challenges to the consumer protection framework in the European Union. As customers become increasingly environmentally conscious, brands are ever more inclined to leverage this interest by invoking the language of environmental protection, sustainable development and climate neutrality. Yet these claims do not always reflect the actual characteristics of their products or services. The EU has sought to bring systemic order to this area by clarifying the information obligations of traders and broadening the list of practices deemed unfair. We consider what these changes mean for businesses in practice.

GLI – AI, Machine Learning & Big Data 2026: The Polish perspective on artificial intelligence law

Global Legal Insights (GLI) is a series of international publications by the Global Legal Group (GLG), authored by legal practitioners from around the world. It offers an up-to-date and highly practical guide to the applicable regulatory landscape, complemented by expert commentary on specific areas of law across different jurisdictions. In short: legislation and actionable know-how in one place.

Banking sector overview | Banking today and tomorrow | May 2026

“The end of the dream of free housing” – this is how the Polish Bank Association (Związek Banków Polskich) has characterised Thursday’s judgments of the Court of Justice of the European Union in cases concerning whether the claims of financial institutions against CHF mortgage borrowers have become time-barred.

Return deposits like VAT? The elephant in the room: the risks of the deposit-return system

The deposit-return system was supposed to be simple. Eco-friendly. Leak-proof. Tax-neutral. However, it took just a few months for serious doubts to emerge. The first loopholes are no longer just theoretical, they are in plain sight. The mechanisms for abuse can be described quite precisely, and the scale of potential losses may be much greater than anticipated. Below, we examine where the system is losing control and how this can be addressed.

Contact us:

Milena Kazanowska – Kędzierska

Milena Kazanowska – Kędzierska

Attorney-at-law / Senior Associate / Energy, Infrastructure, Environment Protection, ESG

+48 539 908 918

m.kazanowska@kochanski.pl