Flexible connections in the new architecture of the EU electricity market

26 June 2024 | Knowledge, News, The Right Focus

Accelerating RES installations and reducing barriers to the realisation of new capacity connections are key challenges in the energy transition process. The European Union has adopted a package amending[1]  the system regulations for the internal electricity market, with the aim of increasing the flexibility of the energy system and adapt the grid infrastructure to the development of distributed RES. Flexible connection agreements are another alternative for projects that have been refused a connection and cannot obtain a commercial connection.

Why the electricity market needs an additional solution for RES connections

The EU energy system is to be made greener by RES and so-called decarbonised gases, and the economy is to be electrified.

Rapidly developing modern technologies and growing investor interest in renewable energy are colliding with outdated energy infrastructure[2] and refusals to connect ,[3] because operators’ development plans do not anticipate the demand for such large volumes of renewable energy.

Connection refusals and the obligation for operators to cooperate with applicants willing to co-finance the connection in the so-called commercial regime do not solve the problem. There is no uniform practice for connecting commercial RES without the risk of discrimination against investors, and sometimes the need for cooperation between operators prolongs the procedure, creates uncertainty and makes the investment unprofitable.

Flexible connection agreements as a so-called third alternative for RES connection

EU Member States will be required to implement regulations aimed at increasing the flexibility of grid operation and generation sources. Solutions such as energy sharing or peak shaving will be introduced.

The electricity system is to become flexible, meaning that it will have the ability to adjust to the variability of generation and consumption patterns and grid availability, across relevant market timeframes[4].

Also key is the introduction of a peak hour, i.e. an hour where, on the basis of the forecasts of transmission system operators, the gross consumption of electricity generated from sources other than renewable sources or the day-ahead wholesale electricity price is expected to be the highest, taking cross-zonal exchanges into account.

Importantly, a flexible connection agreement will be introduced[5], which means a set of agreed conditions for connecting electrical capacity to the grid that includes conditions to limit and control the electricity injection to and withdrawal from the transmission network or distribution network. The agreement will be able to be introduced on the basis of guidelines adopted by the regulatory authority[6] in this regard.

In areas where network capacity for new connections is limited or unavailable, the transmission system operator (TSOe) and distribution system operator (DSOe) will be able to offer flexible connection agreements.

The areas with limited or no capacity will be identified by the TSOe, who will be obliged to publish detailed information in this respect with high spatial granularity, respecting public security and data confidentiality (with monthly updates).[7]

The TSOe shall also be obliged to inform applicants about the status and treatment of connection requests (including information on flexible connection agreements to be provided within three months of the submission of the request). If a connection request is neither granted nor permanently rejected, the TSOe must update the information on the treatment of the request and on the possibilities for flexible connection at least on a quarterly basis.

This solution has the potential to ensure that investors whose connection requests are rejected in situations where the operator fails to negotiate a commercial connection can connect installations under a flexible connection agreement.

The conditions to be met by flexible connection agreements are:

  • No delaying of network reinforcements in identified areas
  • The possibility to convert from flexible to firm connection agreements if the network is developed on the basis of established criteria
  • The application of flexible connection agreements as a permanent solution where the regulatory authority considers that network development in a given area is not the most efficient solution

Flexible connection agreements will have to specify, in particular:

  • The maximum firm injection and withdrawal of electricity to and from the grid, and additional flexible injection and withdrawal capacity that can be connected and differentiated by time blocks throughout the year
  • The network charges applicable to both the firm and flexible injection and withdrawal capacities
  • The agreed duration of the flexible connection agreement and the expected date for granting connection to the entire requested firm capacity

System users connecting under a flexible connection agreement will be required to install a power control system certified by an authorised entity[8].

Entry into force of new regulations

The grid flexibility and flexible connection regulations set out in the package will partially enter into force 20 days after the publication of the Regulation in the Official Journal of the European Union. The remaining part of the rules, which are covered by the Directive, will be implemented within 6 months of the date of entry into force of the Directive (the same date as for the Regulation).

Any questions? Contact us

Wojciech Wrochna

Aleksandra Pinkas

 

[1] Regulation of the European Parliament and of the Council amending Regulations (EU) 2019/942 and (EU) 2019/943 as regards improving the Union’s electricity market design and Directive of the European Parliament and of the Council amending Directives (EU) 2018/2001 and (EU) 2019/944 as regards improving the Union’s electricity market design (the package has been adopted by the EU Council and is awaiting the signature of the EU legislators)

[2]  Supreme Audit Office, Information on the results of the audit. Development of the electricity distribution network, 2024 – the report shows, among other things, that in 2021, 46% of 110 kV (HV) power lines were over 40 years old, half of which were over 50 years old. 

[3]  Bulletin 01/2023 of the Energy Regulatory Office, pp. 72-73 – more than 7,000 negative decisions were issued in 2022 alone, an increase of approximately 88% compared to the previous year

[4] Article 2(79) of Regulation 2019/943

[5] Article 6a of Directive 2019/944

[6] In Poland, the President of the Energy Regulatory Office

[7] Article 50(4a) of Regulation 2019/943

[8] The certification is likely to be made by Polskie Sieci Elektroenergetyczne.

Latest Knowledge

Banking sector overview | Banking today and tomorrow | June 2026

According to a statement published by GPW Benchmark, the reference rate administrator, and the Polish Financial Supervision Authority (KNF), which oversees the administrator, 31 December 2036 will be the last day on which the WIBID and WIBOR rates will be provided for all key fixing periods: 1 month (1M), 3 months (3M) and 6 months (6M).

How to correctly calculate length of service from 1 May 2026

New rules for calculating length of service have applied to private sector employers since the beginning of May 2026. With companies continuing to express concerns about the new framework, the Ministry of Family, Labour and Social Policy has addressed the most common questions. We look at the issues that are (still) troubling employers and how we can help.

Tax settlement agreement: A new tool in the General Tax Code

A draft bill amending the General Tax Code (No. UDER110) has been submitted for consideration by the Council of Ministers. The bill introduces the tax settlement agreement, a new form of amicable dispute resolution between taxpayers and the tax authority. The draft is open for inter-ministerial review and public consultation until 19 June, with the proposed date of entry into force being 1 January 2028. Below, we examine who may apply for a settlement agreement, when, and on what terms, and how the process may work in practice.

A revolutionary reform of Poland’s capital market – ETFs and the Qualified Investment Fund

Poland’s capital market is on the cusp of one of the most significant reforms in recent years, which will fundamentally reshape the regulatory framework for ETFs and introduce an entirely new investment vehicle: the Qualified Investment Fund (QIF/KFI). This is a response to market demands and presents an opportunity for Poland to close the gap with countries such as Luxembourg and Ireland, with the overarching objective of boosting competitiveness and stemming the outflow of investment capital abroad. The new regulations aim to deliver greater flexibility for investors and fund managers alike, while also aligning with current market trends and European standards. We examine what is changing in practice and what it means for all market participants.

Directive 2024/825 – the European Union’s response to greenwashing

Greenwashing poses one of the most significant challenges to the consumer protection framework in the European Union. As customers become increasingly environmentally conscious, brands are ever more inclined to leverage this interest by invoking the language of environmental protection, sustainable development and climate neutrality. Yet these claims do not always reflect the actual characteristics of their products or services. The EU has sought to bring systemic order to this area by clarifying the information obligations of traders and broadening the list of practices deemed unfair. We consider what these changes mean for businesses in practice.

GLI – AI, Machine Learning & Big Data 2026: The Polish perspective on artificial intelligence law

Global Legal Insights (GLI) is a series of international publications by the Global Legal Group (GLG), authored by legal practitioners from around the world. It offers an up-to-date and highly practical guide to the applicable regulatory landscape, complemented by expert commentary on specific areas of law across different jurisdictions. In short: legislation and actionable know-how in one place.

Banking sector overview | Banking today and tomorrow | May 2026

“The end of the dream of free housing” – this is how the Polish Bank Association (Związek Banków Polskich) has characterised Thursday’s judgments of the Court of Justice of the European Union in cases concerning whether the claims of financial institutions against CHF mortgage borrowers have become time-barred.

Return deposits like VAT? The elephant in the room: the risks of the deposit-return system

The deposit-return system was supposed to be simple. Eco-friendly. Leak-proof. Tax-neutral. However, it took just a few months for serious doubts to emerge. The first loopholes are no longer just theoretical, they are in plain sight. The mechanisms for abuse can be described quite precisely, and the scale of potential losses may be much greater than anticipated. Below, we examine where the system is losing control and how this can be addressed.