Guidelines of the URE President on doubts about public and commercial grid connection of RES installations

4 April 2024 | Knowledge, News

The European Union has adopted a binding target of climate neutrality by 2050 and intends to achieve this by, among other things, increasing the share of renewable energy sources (RES) in the energy mix. The share of RES in the EU’s gross final energy consumption should, by 2030, be at least 42.5% (compared to 23% today), with a target of up to 45%.[1]

The EU requires Member States to speed up and simplify procedures for RES projects, including connection procedures. In addition, by 21 February 2026, Member States must designate accelerated RES development areas, with the administrative procedure generally limited to 12 months.

Climate and energy targets in the face of rising connection refusals

In Poland, where renewable energy currently accounts for ca. 18% of energy consumption,[2] the main obstacle to the development of RES investment is the increasing number of connection refusals. According to information published by the President of the Energy Regulatory Office (URE), more than 7,000 negative decisions were issued in 2022 alone, an increase of ca. 88% compared to the previous year.[3]

Furthermore, an audit conducted by the Supreme Audit Office (NIK) between 1 January 2018 and 30 June 2022[4] revealed irregularities in the connection of RES installations. Among other things, it was found that electricity system operators (ESOs) did not take into account connection refusals in planned investments, which was considered an unsound practice. In addition, the NIK report found that the reasons given by the URE President for refusals were not sufficiently detailed and did not allow an assessment of whether a given decision was actually justified. This means that the standardisation of ESO practice is necessary for the further development of renewable energy, as the scale of challenges in this area is enormous.

Conditions for investors to conclude a connection agreement

Pursuant to Article 7(1) of the Energy Law,[5] an electricity transmission system operator (ETSO) or an electricity distribution system operator (EDSO) is obliged to conclude a grid connection agreement, ensuring the equal treatment of all applicants. When the technical and economic conditions for grid connection and energy supply are met, priority should be given to RES installations.

In response to numerous enquiries regarding public-private and commercial connections, the URE President has published information[6] to clarify doubts and to speed up the RES connection procedure.

Non-compliance with technical, economic and technical-economic conditions

According to the information of the URE President, non-compliance with technical conditions will occur only when the technical obstacle is permanent (i.e. cannot be removed by any measures) and objective (results from an irremovable obstacle),[7] i.e. “connection to the grid is impossible in the current and future state of the grid, regardless of expenditure”.

According to the URE President, such situations are “extremely exceptional” and should be described very precisely when the issuing of connection conditions is refused.

Failure to comply with economic conditions, on the other hand, will only occur if the ETSO or EDSO, as the case may be, considers that connection is not possible based on the criterion chosen, including:

  • Connection may result in costs being passed on to consumers.
  • The necessary grid facilities are not included in the network development plan.
  • External financing is not available.

According to the URE President, non-compliance with technical-economic conditions will occur when connection is technically feasible, but the ETSO or EDSO development plan does not provide for the necessary network development and connection can only take place if the applicant co-finances it.

Guidelines of the URE President for commercial connection of RES installations

Applicants whose installation does not meet the economic conditions may apply for a so-called commercial connection referred to in Article 7(9) of the Energy Law. The relevant operator is then obliged to indicate the connection fee, the amount of which should be agreed with the applicant. At the applicant’s request, the ESO should also indicate how this amount is calculated, specifying the main components of investment expenditure.

According to the information of the URE President, a possible dispute between the applicant and the operator does not constitute an obstacle to commercial connection.

Applicants may resubmit their applications, for example by indicating a more favourable connection location. Furthermore, when analysing applications for the issuance of connection conditions, operators are not entitled to assess the correctness or feasibility of the decision on development conditions or to question the possibility of locating a RES installation in the area specified in that decision.

RES: Conclusions and recommendations

  • Accelerated RES development areas will be designated by 21 February 2026. Investors should therefore actively participate in the designation process to have the opportunity to implement RES projects more quickly
  • Connections should only be refused in exceptional circumstances, i.e. if:
    • None of the current or planned measures enable connection [technical criterion], or
    • The operator cannot finance the connection and the necessary grid facilities are not included in the network development plan [economic criterion], or
    • Connection is technically feasible, but the necessary grid expansion is not included in the development plan [technical-economic criterion]
  • In parallel with the pending procedure and in case of a connection refusal, investors may apply for a so-called commercial connection
  • Investors may apply for connection several times, including by indicating a different location, and the ESO should not make the issuing of connection conditions dependent on an assessment of the correctness of the location decision (development conditions)
  • At the investor’s request, the ESO should allow commercial connection, specifying the amount and method of calculation of the connection fee
  • The ESO should increase investment expenditure to improve grid capacity and cooperate with investors applying for commercial connection
  • The URE President should give detailed reasons for refusing to issue connection conditions

Any questions? Contact

Milena Kazanowska-Kędzierska

Aleksandra Pinkas

 

[1] Article 3 of Directive (EU) 2018/2001 of the European Parliament and of the Council of 11 December 2018 on the promotion of the use of energy from renewable sources (OJ L 2018 No. 328 as amended).

[2] Overall share of energy from renewable sources in 2022 [Eurostat data as at December 2023].

[3] URE Bulletin 01/2023, pp. 72-73

[4] NIK, Information on audit results. Development of the electricity distribution grid, 2024.

[5] Act of 10 April 1997 – Energy Law (Journal of Laws 2024, item 266), “EL”.

[6] Information No. 15/2024 of the URE President of 22 March 2024 on the issues causing the most common doubts about grid connection.

[7] Confirmed in the plan for meeting current and future energy demand, drawn up by the ETSO or EDSO, as appropriate, pursuant to Article 16 of the EL.

Latest Knowledge

NIS2 and the National Cybersecurity System Act in transport: what you need to do before October 2026

The amended Act on the National Cybersecurity System (UKSC) has been in force since 3 April 2026. For transport sector undertakings, this means a specific compliance timeline, including an obligation to register with the National Cybersecurity System (KSC) registry by 3 October 2026. Failure to do so may result in substantial financial penalties, coupled with the risk of personal liability for senior management. Not every undertaking, however, automatically falls within the scope of the new regime. Read on to find out whether your organisation is affected and what you need to do before the deadline for preparation.

Family foundations: the government has done the maths and presented the bill

Three years. That’s how long we’ve been waiting for what the Council of Ministers had seen in the data from the outset – and has now disclosed in its review of the Family Foundation Act. The document not only diagnoses the problems, but also previews substantial changes to rules that founders and their advisers treated as settled and stable. And therein lies a problem that goes far beyond tax matters. If the rules of the game are changed while the game is being played, there can be neither planning stability nor trust in the law. It is no coincidence that one of the greatest concerns among entrepreneurs considering setting up a foundation is not the level of taxation, but the stability of the legal framework – which today is once again being called into question.

What the new swiss franc act means for banks

We now have a new Act on Special Measures for the Adjudication of Cases Concerning Loan Agreements Denominated in or Indexed to the Swiss Franc. The provisions come into force 14 days after publication. So now is a good time to look at what lies ahead and what banks should be doing today.

New draft Pay Transparency Act – what has changed since December 2025?

A second version of the draft act on strengthening the application of the right to equal pay for equal work or work of equal value between men and women has now been published. It refines procedures and deadlines and introduces a new supervisory body. We have already discussed the changes affecting the recruitment stage and the three pillars of the forthcoming pay transparency framework, noting that Poland will miss the EU transposition deadline of 7 June 2026. Now, we take a closer look at the further changes, new developments and risks that have emerged in the latest, April version of the draft.

Payment Services Regulation (PSR) – between consumer protection and due diligence

The draft Payment Services Regulation (PSR) is one of the most significant elements of the reform of the EU legal framework for payment services. Its principal aim is to enhance the security of cashless transactions and to reduce the scale of financial fraud, in particular that arising from the growth of digital channels. At the same time, the new rules are intended to introduce a liability model that will not result in risk being transferred entirely to financial institutions, whilst retaining an important role for independent due diligence on the part of the user.

Energy deregulation – key changes for businesses and energy consumers

The President has now signed the Energy Deregulation Act (UDER92). The new provisions cover both the relationships between energy undertakings and consumers, and matters relating to investment, district heating, and the administrative obligations of energy market participants. The Act introduces changes in the areas of billing, communication with consumers, grid connection, and the operations of undertakings in the energy and district heating sectors. We set out the key points to note.

Banking sector overview | Banking today and tomorrow | July 2026

Under the draft legislation, banks will be required to offer existing borrowers a switch from WIBOR-based to POLSTR-based interest rates, a mechanism intended to speed up the voluntary transition of financial instruments to the new benchmark. The banking sector has responded positively to the proposal, according to Tadeusz Białek, President of the Polish Bank Association.

“Withdraw from contract here” – what next for the new button in online shops, on trading platforms and in mobile apps?

From 19 June, national legislation was to require businesses in the European Union entering into distance contracts with consumers via an online interface to provide consumers with the option to withdraw from the contract via a dedicated function/button. However, due to Poland’s delay in transposing Directive 2023/2673, which requires the use of such a button, this obligation has been postponed in our country. We look at what remote contract withdrawal entails and which transactions the new feature will apply to.

Municipal master plans – new deadline, same old challenges

On 11 June 2026, the President signed into law a bill extending the deadline for municipalities to adopt their master plans (plany ogólne). The key deadline for adopting master plans was moved from 30 June to 31 August 2026. We examine the reasons behind this change and consider what the absence of a master plan might mean for potential investors and their future projects.