Electricity distribution licences – the most common problems and application mistakes

20 November 2024 | Knowledge, News, The Right Focus

Companies applying for an electricity distribution licence (Polish: DEE) face various challenges in obtaining it. Very often, the reason for the refusal of such a licence is the submission of inappropriate connection conditions.

This is because, in practice, the President of the Energy Regulatory Office (ERO) requires the submission of an agreement/conditions for the connection of the distribution network to the transmission network of a TSO or to the distribution network of the relevant DSO.

This implies two possible scenarios:

  • Submission of a correct application to the TSO or the relevant DSO for the issuing of conditions for the connection of the distribution network to the transmission network or the distribution network, as the case may be, or;
  • If the conversion of the receiving/generating system to the company’s distribution network takes place after the connection to the facility has already been made, a new application for connection conditions must be submitted and a new agreement concluded. Alternatively, an attempt can be made to resolve the matter by way of an agreement. In such a situation, the course of action will largely depend on the decision of the relevant DSO or TSO.

In certain cases, the President of the ERO will recognise agreements between the parties regulating the issue of changing the type of connected system and the related settlements. However, such an agreement should clearly indicate the boundary between the receiving/generating system and the distribution network.

It should be borne in mind that a change in the type of connection may also entail a change in the fee for that connection.

Therefore, there is a further risk that, in the event of a change of connection from a receiving or generating system to a distribution network, due to the connection of a new type of facility (network), there will be an obligation to pay the network connection fee (with a possible deduction of the amount already paid when the system was first connected).

Consequences of submitting an improperly prepared DEE licence application

The submission of documents in the form of a connection agreement for the connection of a facility other than a distribution network should result in the entrepreneur being requested to remedy formal deficiencies and present the agreement for the connection of the distribution network to the grid within the deadline set by the President of the ERO.

In the case of a completed connection, there is a risk that the DSO or TSO and the prospective licensee will not be able to reach an agreement on a change in the nature of the connection within the deadline set by the President of the ERO. It is therefore advisable to negotiate this issue before submitting the licence application. A mistake at this stage, i.e. submitting the application without the relevant annex, may result in the licence being refused on the grounds that the deadline for remedying formal deficiencies has not been met.

It should also be noted that a change in the type of connection (a network instead of a facility) may result in a change in the fee. Entrepreneurs deciding to develop or implement a new business should take this into account in their plans.

Any questions? Contact us

Milena Kazanowska-Kędzierska

Latest Knowledge

Banking sector overview | Banking today and tomorrow | July 2026

Under the draft legislation, banks will be required to offer existing borrowers a switch from WIBOR-based to POLSTR-based interest rates, a mechanism intended to speed up the voluntary transition of financial instruments to the new benchmark. The banking sector has responded positively to the proposal, according to Tadeusz Białek, President of the Polish Bank Association.

“Withdraw from contract here” – what next for the new button in online shops, on trading platforms and in mobile apps?

From 19 June, national legislation was to require businesses in the European Union entering into distance contracts with consumers via an online interface to provide consumers with the option to withdraw from the contract via a dedicated function/button. However, due to Poland’s delay in transposing Directive 2023/2673, which requires the use of such a button, this obligation has been postponed in our country. We look at what remote contract withdrawal entails and which transactions the new feature will apply to.

Municipal master plans – new deadline, same old challenges

On 11 June 2026, the President signed into law a bill extending the deadline for municipalities to adopt their master plans (plany ogólne). The key deadline for adopting master plans was moved from 30 June to 31 August 2026. We examine the reasons behind this change and consider what the absence of a master plan might mean for potential investors and their future projects.

Record fines and the upcoming 21st sanctions package – what should businesses expect?

The past year has brought a series of enforcement actions that clearly signal a tightening approach by the Polish customs and revenue authorities towards breaches of the sanctions regime. Importantly, businesses should already be preparing for further changes, as the European Union has announced its 21st sanctions package and updated the list of designated persons and entities. We examine the key developments and offer guidance on how to minimise the risk of non-compliance.

A sea change in the rules governing board members’ liability for a company’s tax arrears

The bill amending the General Tax Code (No. UC138) fundamentally overhauls the rules governing the tax liability of third parties for capital companies’ tax arrears.  It comes in response to recent CJEU judgments, the Ombudsman’s February statement and the post-audit report of the Supreme Chamber of Audit (NIK) of December 2025. We examine what’s changing, who will be affected by the new rules and what steps are worth taking right now.

Partner in name, but only if male: the linguistic trap in Polish corporate law

One of the structures available under Polish law is the ‘spółka partnerska’ (professional partnership), modelled on the Anglo-Saxon Limited Liability Partnership. As defined in the Polish Commercial Companies Code, this is a vehicle for individuals practising liberal professions, such as doctors, architects and accountants. And yet, the provisions governing professional partnerships make no mention of their applicability to women. We therefore examine whether there is no room for female partners, feminine-gendered forms, or simply linguistic empathy.

Can you sue over words aimed at an entire community?

A damaging public statement does not necessarily refer to a specific individual. Sometimes, the author attributes negative characteristics to a whole group of people, portrays them as a threat or uses language that could be seen as demeaning. Statements of this kind frequently concern LGBTQ+ people. This raises the question: can a member of the targeted community bring a lawsuit seeking compensation or an apology, even if they were not named directly? We decided to look into this.

Banking sector overview | Banking today and tomorrow | June 2026

According to a statement published by GPW Benchmark, the reference rate administrator, and the Polish Financial Supervision Authority (KNF), which oversees the administrator, 31 December 2036 will be the last day on which the WIBID and WIBOR rates will be provided for all key fixing periods: 1 month (1M), 3 months (3M) and 6 months (6M).

How to correctly calculate length of service from 1 May 2026

New rules for calculating length of service have applied to private sector employers since the beginning of May 2026. With companies continuing to express concerns about the new framework, the Ministry of Family, Labour and Social Policy has addressed the most common questions. We look at the issues that are (still) troubling employers and how we can help.