Electricity distribution licences – the most common problems and application mistakes

20 November 2024 | Knowledge, News, The Right Focus

Companies applying for an electricity distribution licence (Polish: DEE) face various challenges in obtaining it. Very often, the reason for the refusal of such a licence is the submission of inappropriate connection conditions.

This is because, in practice, the President of the Energy Regulatory Office (ERO) requires the submission of an agreement/conditions for the connection of the distribution network to the transmission network of a TSO or to the distribution network of the relevant DSO.

This implies two possible scenarios:

  • Submission of a correct application to the TSO or the relevant DSO for the issuing of conditions for the connection of the distribution network to the transmission network or the distribution network, as the case may be, or;
  • If the conversion of the receiving/generating system to the company’s distribution network takes place after the connection to the facility has already been made, a new application for connection conditions must be submitted and a new agreement concluded. Alternatively, an attempt can be made to resolve the matter by way of an agreement. In such a situation, the course of action will largely depend on the decision of the relevant DSO or TSO.

In certain cases, the President of the ERO will recognise agreements between the parties regulating the issue of changing the type of connected system and the related settlements. However, such an agreement should clearly indicate the boundary between the receiving/generating system and the distribution network.

It should be borne in mind that a change in the type of connection may also entail a change in the fee for that connection.

Therefore, there is a further risk that, in the event of a change of connection from a receiving or generating system to a distribution network, due to the connection of a new type of facility (network), there will be an obligation to pay the network connection fee (with a possible deduction of the amount already paid when the system was first connected).

Consequences of submitting an improperly prepared DEE licence application

The submission of documents in the form of a connection agreement for the connection of a facility other than a distribution network should result in the entrepreneur being requested to remedy formal deficiencies and present the agreement for the connection of the distribution network to the grid within the deadline set by the President of the ERO.

In the case of a completed connection, there is a risk that the DSO or TSO and the prospective licensee will not be able to reach an agreement on a change in the nature of the connection within the deadline set by the President of the ERO. It is therefore advisable to negotiate this issue before submitting the licence application. A mistake at this stage, i.e. submitting the application without the relevant annex, may result in the licence being refused on the grounds that the deadline for remedying formal deficiencies has not been met.

It should also be noted that a change in the type of connection (a network instead of a facility) may result in a change in the fee. Entrepreneurs deciding to develop or implement a new business should take this into account in their plans.

Any questions? Contact us

Milena Kazanowska-Kędzierska

Latest Knowledge

Protecting yourself against tax risks in the deposit-return system

The deposit-return system has been in place since October 2025, raising significant tax concerns from the outset. Although the regulations came into force, it was unclear for a long time how to apply them in practice. Some of the regulations needed clarification, some solutions were missing and the published explanations did not cover all the key issues. Consequently, the market began to develop its own operating standards.

Banking sector overview | Banking today and tomorrow | March 2026

On 12 February 2026, the Court of Justice of the European Union (CJEU) issued a judgment concerning the use of the WIBOR index in loan agreements. The CJEU judges confirmed that, in consumer cases, courts cannot examine the correctness of the WIBOR calculation. The banks had correctly informed their clients about the reference rate in accordance with national and EU law.

The issue of the National Labour Inspectorate reform has resurfaced

A new draft law proposing changes to the way the National Labour Inspectorate operates has been submitted to the Sejm. During its first reading on 25 February, the draft was not rejected and was therefore referred to the Social Policy and Family Committee for further consideration. Despite the concerns and controversies raised so far, including by businesses, the legislature continues to pursue the thorough modernisation of Poland’s employment model, which involves increased supervision of the labour market and curbing the abuse of civil law contracts. In this article, we will take a look at the proposals included in the new draft and explain what they mean for businesses.

Polish AI boom

According to the latest data, nearly 15,000 companies dealing with artificial intelligence were registered in Poland in 2025.[1] This testifies to an undoubted boom in AI, as well as to the dynamic changes related to the development of this technology. However, amid the rush to implement AI, do companies consider the most important issue: securing the outcomes of their work and protecting themselves against competitors? In this article, we explore this issue and suggest ways to avoid costly problems.

Length of service now includes periods of self-employment

The length of service no longer depends solely on work carried out under a contract of employment. The amendment to the Labour Code introduces significant changes, as work carried out under civil law contracts or as part of business activity will now also be included when calculating service, which affects employees’ rights. What will this mean for employees and employers?

Banking sector overview | Banking today and tomorrow | February 2026

The Polish banking sector is undergoing intense reshuffling on a scale not seen for years. Large banks are changing owners, foreign players are shifting their strategies and new investors are entering the market. The question is whether these are just temporary shifts in capital or the beginning of lasting change in the industry’s balance of power.

31 January. Don’t forget about the DAC7 Directive

The deadline for meeting the obligations under the DAC7 directive and the Polish regulations implementing it is fast approaching. Online platform operators must fulfil their reporting obligations by 31 January 2026 at the latest with regard to 2025 data. For many, this is the final opportunity not only to prepare the required information, but also to verify whether DAC7 obligations apply to them and, if so, to what extent.

Contact us:

Milena Kazanowska – Kędzierska

Milena Kazanowska – Kędzierska

Attorney-at-law / Senior Associate / Energy, Infrastructure, Environment Protection, ESG

+48 539 908 918

m.kazanowska@kochanski.pl